[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140856":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1140856,799,2,"多选题","建设工程设计方的项目管理工作涉及（ ）阶段。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","设计前的准备",true,{"key":16,"text":17,"correct":14},"B","设计",{"key":19,"text":20,"correct":21},"C","决策",false,{"key":23,"text":24,"correct":14},"D","施工",{"key":26,"text":27,"correct":14},"E","动用前准备","ABDE","本题主要考查建设工程设计方的项目管理工作。 设计方项目管理的任务包括：与设计工作有关的安全管理设计成本控制和与设计工作有关的工程造价控制、设计进度控制、设计质量控制、设计合同管理、设计信息管理和设计工作有关的组织和协调。设计方的项目管理工作主要在设计阶段进行，但也涉及到设计前的准备阶段、施工阶段、动用前准备阶段和保修期。 综上所述，本题正确答案为ABDE。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]