[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140855":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1140855,799,2,"多选题","供货方的项目管理工作主要在施工阶段进行，但它也涉及（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","设计准备阶段",true,{"key":16,"text":17,"correct":14},"B","设计阶段",{"key":19,"text":20,"correct":14},"C","动用前准备阶段",{"key":22,"text":23,"correct":14},"D","保修期",{"key":25,"text":26,"correct":27},"E","运营阶段",false,"ABCD","本题主要考查施工过程质量验收。 供货方的项目管理工作主要在施工阶段进行，但它也涉及设计准备阶段、设计阶段、动用前准备阶段、保修期。 综上所述，本题正确答案为ABCD。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]