[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140837":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1140837,799,1,"单选题","建设项目工程总承包方的工作程序中，进行项目策划、编制项目计划属于项目（ ）阶段的工作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","启动",false,{"key":16,"text":17,"correct":18},"B","初始",true,{"key":20,"text":21,"correct":14},"C","设计",{"key":23,"text":24,"correct":14},"D","施工","本题主要考查建设项目工程总承包方的工作程序。建设项目工程总承包方的工作程序如下： 综上所述，本题正确选项为B项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]