[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140834":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1140834,799,1,"单选题","按照国际工程的惯例，当建设工程采用指定分包时，（ ）应对分包工程的工期目标和质量目标负责。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","业主方",false,{"key":16,"text":17,"correct":14},"B","监理方",{"key":19,"text":20,"correct":21},"C","施工总承包方",true,{"key":23,"text":24,"correct":14},"D","劳务分包方","本题考核的是施工方项目管理的目标。 按国际工程的惯例，当采用指定分包商时，不论指定分包商与施工总承包方，或与施工总承包管理方，或与业主方签订合同，由于指定分包商在签约前必须得到施工总承包方或施工总承包管理方的认可，因此，施工总承包方或施工总承包管理方应对合同规定的工期目标和质量目标负责。 综上所述，正确选项为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]