[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140825":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1140825,799,2,"多选题","根据《建设工程监理规范》(GB\u002FT50319—2013)，工程建设监理规划应在（ ）后开始编制。 2016",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","第一次工地会议",false,{"key":16,"text":17,"correct":14},"B","建设单位指定日期",{"key":19,"text":20,"correct":21},"C","签订委托监理合同",true,{"key":23,"text":24,"correct":14},"D","施工单位进场",{"key":26,"text":27,"correct":21},"E","收到设计文件","CE","本题考查的是监理的工作方法。工程建设监理规划应在签订委托监理合同及收到设计文件后开始编制，完成后必须经监理单位技术负责人审核批准，并应在召开第一次工地会议前报送业主。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]