[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140787":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1140787,799,1,"单选题","下列项目风险管理工作中，属于风险响应的是（ ）。 2016",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","收集与项目风险有关的信息",false,{"key":16,"text":17,"correct":14},"B","监控可能发生的风险并提出预警",{"key":19,"text":20,"correct":14},"C","确定各种风险的风险量和风险等级",{"key":22,"text":23,"correct":24},"D","向保险公司投保难以控制的风险",true,"本题考查的是项目风险管理的工作流程。选项A属于风险识别；选项B属于风险控制；选项C属于风险评估。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]