[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140774":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1140774,799,1,"单选题","下列影响建设工程项目实施的风险因素中，属于技术风险的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程勘查资料",true,{"key":16,"text":17,"correct":18},"B","气象条件",false,{"key":20,"text":21,"correct":18},"C","公用防火设施的数量",{"key":23,"text":24,"correct":18},"D","人身安全控制计划","本题考查的是项目风险类型的内容。 技术风险包括：工程勘察资料和有关文件；工程设计文件；工程施工方案；工程物资；工程机械等。 A项：工程勘查资料属于技术风险，故当选。 B项：气象条件属于工程环境风险，故不当选。 CD项：公用防火设施的数量、人身安全控制计划属于经济与管理风险，故不当选。 综上所述，本题正确选项为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]