[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140761":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1140761,799,2,"多选题","国际工程施工中的质量管理由（ ）主管。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":18},"B","承包人的项目经理",true,{"key":20,"text":21,"correct":18},"C","承包人指定的技术副经理",{"key":23,"text":24,"correct":14},"D","工程师",{"key":26,"text":27,"correct":18},"E","承包人指定的总工程师","BCE","本题主要考查施工质量管理的负责人。 BCE项：国际工程施工中的质量管理由承包人的项目经理或者承包人指定的技术副经理或者承包人的总工程师主管。所以BCE项正确。 A项：发包人将项目的施工工作委托给承包人，施工过程中的质量管理应有承包人负责，而非发包人。所以A项错误。 D项：工程师一般指业主方或受业主方委托对项目施工过程进行监督、管理的人员，但不是施工中质量管理的主体。所以D项错误。 综上所述，本题正确选项为BCE项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]