[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140758":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1140758,799,1,"单选题","下列项目目标动态控制的流程中，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","收集项目目标的实际值&rarr;实际值与计划值比较&rarr;找出偏差&rarr;采取纠偏措施",true,{"key":16,"text":17,"correct":18},"B","收集项目目标的实际值&rarr;实际值与计划值比较&rarr;找出偏差&rarr;进行目标调整",false,{"key":20,"text":21,"correct":18},"C","收集项目目标的实际值&rarr;实际值与计划值比较&rarr;采取控制措施&rarr;进行目标调整",{"key":23,"text":24,"correct":18},"D","实际值与计划值比较&rarr;找出偏差&rarr;采取控制措施&rarr;收集项目目标的实际值","本题考查的是项目目标动态控制的工作程序。收集项目目标的实际值，如实际投资，实际进度等；定期（如每两周或每月）进行项目目标的计划值和实际值的比较；通过项目目标的计划值和实际值的比较，如有偏差，则采取纠偏措施进行纠偏。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]