[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140756":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1140756,799,1,"单选题","根据政府主管部门有关建设工程劳动用工管理规定，建筑施工企业应将项目作业人员有关情况在当地建筑业企业信息管理系统中如实填报，人员发生变更的，应在变更后（）个工作日内做相应变更。2018真题",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","30",false,{"key":16,"text":17,"correct":14},"B","15",{"key":19,"text":20,"correct":14},"C","14",{"key":22,"text":23,"correct":24},"D","7",true,"本题考查的是施工企业劳动用工和工资支付管理。建筑施工企业应当将每个工程项目中的施工管理、作业人员劳务档案中有关情况在当地建筑业企业信息管理系统中按规定如实填报。人员发生变更的，应当在变更后7个工作日内，在建筑业企业信息管理系统中作相应变更。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]