[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140719":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1140719,799,1,"单选题","根据《建设工程项目管理规范》（GB \u002F T50326 - 2006），项目管理目标责任书应在项目实施之前，由（ ）制定。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目技术负责人",false,{"key":16,"text":17,"correct":14},"B","法定代表人",{"key":19,"text":20,"correct":14},"C","项目经理与项目承包人协商",{"key":22,"text":23,"correct":24},"D","法定代表人与项目经理协商",true,"本题主要考查了施工企业项目经理的责任。 根据《建设工程项目管理规范》（GB \u002F T50326 - 2006），项目管理目标责任书应在项目实施之前，由法定代表人或其授权人与项目经理协商制定。 综上所述，本题正确答案为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]