[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140717":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1140717,799,1,"单选题","编制项目管理目标责任书应依据的资料不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织的管理制度项目合同文件",false,{"key":16,"text":17,"correct":18},"B","项目招标文件",true,{"key":20,"text":21,"correct":14},"C","项目管理规划大纲",{"key":23,"text":24,"correct":14},"D","组织的经营方针和目标","本题主要考查项目管理目标责任书。 项目管理目标责任书是由企业法定代表人根据施工合同和经营管理目标要求明确规定项目经理部应达到的成本、质量、进度和安全等控制目标的文件。编制依据包括（1）项目合同文件；（2）组织的管理制度；（3）项目管理规划大纲；（4）组织的经营方针和目标。 项目招标文件不属于编制依据。 本题为选非题，综上所述，本题正确答案为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]