[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140713":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1140713,799,1,"单选题","根据动态控制原理，项目目标动态控制的第一步工作是（ ）。 2016",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","调整项目目标",false,{"key":16,"text":17,"correct":18},"B","分解项目目标",true,{"key":20,"text":21,"correct":14},"C","制定纠偏措施",{"key":23,"text":24,"correct":14},"D","收集项目目标实际值","本题考查的是项目目标动态控制的方法及其应用。动态控制第一步，项目目标动态控制的准备工作：将项目的目标进行分解，以确定用于目标控制的计划值。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]