[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140699":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1140699,799,1,"单选题","下列各项中属于施工过程中的投资的计划值和实际值的比较的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程概算和投资规划的比较",false,{"key":16,"text":17,"correct":14},"B","工程预算和投资规划的比较",{"key":19,"text":20,"correct":14},"C","工程概算和预算的比较",{"key":22,"text":23,"correct":24},"D","合同价与工程概算的比较",true,"本题主要考查投资的计划值和实际值的比较。@##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]