[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140696":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1140696,799,1,"单选题","应用动态控制原理控制项目投资时，属于设计过程中投资的计划值与实际值比较的是（）。2018真题",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程概算与工程合同价",false,{"key":16,"text":17,"correct":14},"B","工程预算与工程合同价",{"key":19,"text":20,"correct":21},"C","工程预算与工程概算",true,{"key":23,"text":24,"correct":14},"D","工程概算与工程决算","本题考查的是动态控制在投资控制中的应用。在设计过程中投资的计划值和实际值的比较即工程概算与投资规划的比较，以及工程预算与概算的比较。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]