[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140693":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1140693,799,2,"多选题","运用动态控制原理控制建设工程项目投资，可以采取的纠偏措施有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","调整施工进度计划",false,{"key":16,"text":17,"correct":18},"B","调整投资控制的方法和手段",true,{"key":20,"text":21,"correct":18},"C","应用价值工程的方法",{"key":23,"text":24,"correct":18},"D","制定节约投资的奖励措施",{"key":26,"text":27,"correct":18},"E","优化施工方法","BCDE","本题主要考查投资动态控制的方法。 通过项目投资计划值和实际值的比较，如发现偏差，则必须采取相应的纠偏措施进行纠偏，如：采取限额设计的方法、调整投资控制的方法和手段、采用价值工程的方法、制定节约投资的奖励措施、调整或修改设计，优化施工方法等。 综上所述，本题正确选项为BCDE项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]