[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140692":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1140692,799,2,"多选题","建设工程项目施工过程中，投资的实际值和计划值的的比较包括（ ）的比较。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程概算与投资规划",false,{"key":16,"text":17,"correct":14},"B","工程预算与工程概算",{"key":19,"text":20,"correct":21},"C","工程合同价与工程概算",true,{"key":23,"text":24,"correct":21},"D","工程款支付与工程概算",{"key":26,"text":27,"correct":21},"E","工程决算与工程概算","CDE","* 本题主要考查施工成本控制。 在施工过程中投资的实际值和计划值的比较包括： （1）工程合同价与工程概算的比较； （2）工程合同价与工程预算的比较； （3）工程款支付与工程概算的比较； （4）工程款支付与工程合同价的比较； （5）工程决算与工程概算、工程预算和工程合同价的比较。 综上所述，本题正确答案为CDE。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]