[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140690":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1140690,799,1,"单选题","应用动态控制原理控制建设工程项目施工成本时，若将工程进度款作为实际值，则可作为计划值的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程合同价",true,{"key":16,"text":17,"correct":18},"B","工程变更款",false,{"key":20,"text":21,"correct":18},"C","工程索赔款",{"key":23,"text":24,"correct":18},"D","工程结算价","本题主要考查施工成本控制。 在施工过程中投资的实际值和计划值的比较包括： 投资的计划值和实际值是相对的，如：相对于工程预算而言，工程概算是投资的计划值；相对于工程合同价，则工程概算和工程预算都可以作为投资的计划值等。本题中，工程进度款属于工程款支付的情况，因此其对应的计划值为工程合同价。 综上所述，本题正确选项为A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]