[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140689":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1140689,799,1,"单选题","应用动态控制原理控制项目投资时，若将工程合同价作为投资实际值，则可作投资计划值的是（）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程概算的工程款支付值",false,{"key":16,"text":17,"correct":14},"B","工程概算和工程决算",{"key":19,"text":20,"correct":14},"C","工程决算和工程款支付值",{"key":22,"text":23,"correct":24},"D","工程概算和工程预算",true,"本题主要考查投资的计划值和实际值的比较。 投资的计划值和实际值的比较如下表所示： 投资的计划值和实际值是相对的，相对于工程合同价，工程概算和工程预算都可作为投资的计划值。 综上所述，本题正确选项为D项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]