[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140687":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1140687,799,2,"多选题","下列具体情况中，施工组织设计应及时进行修改或补充的有（）。2018真题",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","由于施工规范发生变更导致需要调整预应力钢筋施工工艺",true,{"key":16,"text":17,"correct":14},"B","由于国际钢材市场价格大涨导致进口钢材无法及时供料，严重影响工程施工",{"key":19,"text":20,"correct":14},"C","由于自然灾害导致工期严重滞后",{"key":22,"text":23,"correct":24},"D","设计单位应业主要求对工程设计图纸进行了细微修改",false,{"key":26,"text":27,"correct":14},"E","施工单位发现设计图纸存在严重错误，无法继续施工","ABCE","本题考查的是施工组织设计的动态管理。项目施工过程中，发生以下情况之一时，施工组织设计应及时进行修改或补充：工程设计有重大修改；有关法律、法规、规范和标准实施、修订和废止；主要施工方法有重大调整；主要施工资源配置有重大调整；施工环境有重大改变。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]