[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140684":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1140684,799,2,"多选题","应用动态控制原理控制建设工程项目进度时，可采取的组织措施包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","调整项目任务分工",true,{"key":16,"text":17,"correct":18},"B","改进进度控制手段",false,{"key":20,"text":21,"correct":14},"C","调整项目管理职能分工",{"key":23,"text":24,"correct":14},"D","改进工作流程",{"key":26,"text":27,"correct":18},"E","改进施工方法","ACD","本题主要考查进度控制的措施。 项目目标动态控制的纠偏措施主要包括： ACD项：属于组织措施。故ACD正确。 B项：属于管理措施。所以B项错误。 E项：属于技术措施。所以E项错误。 综上所述，本题正确选项是ACD项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]