[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140683":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1140683,799,2,"多选题","应用动态控制原理进行目标控制时，用于纠偏的组织措施包括（ ）等。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","调整进度管理的方法",false,{"key":16,"text":17,"correct":18},"B","调整招标工作的管理职能分工",true,{"key":20,"text":21,"correct":18},"C","调整投资控制工作流程",{"key":23,"text":24,"correct":14},"D","更换不同的软件编制施工进度计划",{"key":26,"text":27,"correct":18},"E","调整合同管理任务分工","BCE","本题主要考查项目目标动态控制的纠偏措施。 项目目标动态控制的纠偏措施主要包括： BCE项：属于组织措施。故BCE正确。 A项：属于管理措施。故A错误。 D项：属于技术措施。故D错误。 综上所述，本题正确答案为BCE 。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]