[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140679":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1140679,799,1,"单选题","建设工程项目目标动态控制的核心是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","合理确定计划值",false,{"key":16,"text":17,"correct":14},"B","认真收集实际值",{"key":19,"text":20,"correct":14},"C","适当调整工程项目目标",{"key":22,"text":23,"correct":24},"D","比较分析，采取纠偏措施",true,"本题主要考查项目目标的动态控制。 项目目标动态控制的核心是，在项目实施的过程中定期地进行项目目标的计划值和实际值的比较，当发现项目目标偏离时采取纠偏措施。 综上所述，本题正确答案为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]