[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140677":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1140677,799,1,"单选题","施工项目经理检查施工进度时，发现施工进度滞后是由于其自身材料采购的原因造成的，则为纠正进度偏差可以采取的组织措施是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","调整采购部门管理人员",true,{"key":16,"text":17,"correct":18},"B","调整材料采购价格",false,{"key":20,"text":21,"correct":18},"C","增加材料采购的资金投入",{"key":23,"text":24,"correct":18},"D","变更材料采购合同","本题考核的是项目的进度控制。 项目目标动态控制的纠偏措施分为：组织措施；管理措施；经济措施；技术措施。 由于检查施工进度落后，发现是自身材料采购原因，调整采购部门管理人员属于组织措施中调整项目管理班子成员。 综上所述，正确选项为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]