[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140676":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1140676,799,1,"单选题","在项目目标动态控制的工作程序中，第一步工作内容是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目决策策划",false,{"key":16,"text":17,"correct":14},"B","制定纠偏措施",{"key":19,"text":20,"correct":21},"C","目标分解",true,{"key":23,"text":24,"correct":14},"D","收集实际数据","本题考核的是动态控制的步骤。 运用动态控制原理控制进度的步骤如下： （1）工程进度目标的逐层分解； （2）在项目实施过程中对工程项目目标进行动态跟踪和控制； （3）如有必要（即发现原定的工程进度目标不合理，或原定的工程进度目标无法实现等），则调整工程进度目标。 综上所述，正确选项为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]