[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140672":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1140672,799,1,"单选题","某工程项目通过调整进度管理的方法和手段来对项目目标进行纠偏，属于纠偏措施中的（ ）措施。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","技术",false,{"key":16,"text":17,"correct":18},"B","管理",true,{"key":20,"text":21,"correct":14},"C","组织",{"key":23,"text":24,"correct":14},"D","经济","本题主要考查纠偏措施。 项目目标动态控制的纠偏措施主要包括： 调整进度管理的方法和手段来对项目目标进行纠偏，属于纠偏措施中的管理措施。 综上所述，本题正确选项是B项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]