[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140671":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1140671,799,1,"单选题","对项目进度管理的方法和手段进行调整，是项目目标动态控制的（ ）措施。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","经济",false,{"key":16,"text":17,"correct":18},"B","管理",true,{"key":20,"text":21,"correct":14},"C","技术",{"key":23,"text":24,"correct":14},"D","组织","本题主要考查对管理措施的理解。 项目目标动态控制的纠偏措施管理措施（包括合同措施），是分析由于管理的原因而影响项目目标实现的问题，并采取相应的措施，如调整进度管理的方法和手段，改变施工管理和强化合同管理等。 综上所述，本题正确答案为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]