[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140652":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1140652,799,2,"多选题","下列项目目标动态控制的纠偏措施中，属于技术措施的有（ ）",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","调整工作流程组织",false,{"key":16,"text":17,"correct":14},"B","调整进度管理的方法和手段",{"key":19,"text":20,"correct":21},"C","改变施工机具",true,{"key":23,"text":24,"correct":21},"D","改变施工方法",{"key":26,"text":27,"correct":14},"E","调整项目管理职能分工","CD","技术措施，分析由于技术（包括设计和施工的技术）的原因而影响项目目标实现的问题，并采取相应的措施，如调整设计、改进施工方法和改变施丁机具等。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]