[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140650":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1140650,799,1,"单选题","项目管理实施计划的编制过程包括：①熟悉相关法规和文件；②分析项目条件和环境；③履行报批手续；④组织编制。2014根据《建设工程项目管理规范》（GB\u002FT50326—2006），正确的编制程序是（ ）。2014",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①→②→③→④",false,{"key":16,"text":17,"correct":18},"B","②→①→④→③",true,{"key":20,"text":21,"correct":14},"C","①→②→④→③",{"key":23,"text":24,"correct":14},"D","②→①→③→④","本题考查的是项目管理实施计划的编制过程。编制项目管理实施规划应遵循下列程序：（1）了解项目相关各方的要求；（2）分析项目条件和环境；（3）熟悉相关法规和文件；（4）组织编制；（5）履行报批手续。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]