[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140646":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1140646,799,1,"单选题","建设工程项目的施工组织方案中需要决定和安排( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工程序和工艺顺序",true,{"key":16,"text":17,"correct":18},"B","施工工艺和施工方法",false,{"key":20,"text":21,"correct":18},"C","工艺顺序和施工方法",{"key":23,"text":24,"correct":18},"D","施工流向和施工工艺","施工组织方案是指施工程序、工艺顺序、施工流向、劳动组织方面的决定和安排。@jin",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]