[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140629":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1140629,799,2,"多选题","项目管理实施规划的编制依据有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","项目条件和环境分析资料",true,{"key":16,"text":17,"correct":14},"B","同类项目的相关资料",{"key":19,"text":20,"correct":14},"C","项目管理实施规划大纲",{"key":22,"text":23,"correct":14},"D","工程合同及相关文件",{"key":25,"text":26,"correct":27},"E","可行性研究报告",false,"ABCD","本题主要考查工程项目管理实施规划编制依据。 项目管理实施规划编制依据有四项，包括： （1）项目管理实施规划大纲， （2）项目条件和环境分析资料； （3）工程合同及相关文件； （4）同类项目的相关资料 综上所述，本题正确答案为ABCD。@jin",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]