[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140623":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1140623,799,1,"单选题","根据《建设工程项目管理规范》（GB\u002FT50326-2006），项目管理规划包括（ ）。( 2015真题 )",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目管理规划原则和内容",false,{"key":16,"text":17,"correct":14},"B","项目管理规划大纲和配套措施",{"key":19,"text":20,"correct":14},"C","项目管理规划大纲和实施大纲",{"key":22,"text":23,"correct":24},"D","项目管理规划大纲和实施规划",true,"本题考查的是项目管理规划的内容。项目管理规划应包括项目管理规划大纲和项目管理实施规划两类文件。选项D是正确的。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]