[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140588":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1140588,799,1,"单选题","关于建设工程项目施工总承包管理模式的说法，正确的是（ ）。( 2015真题 )",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工总承包管理单位应参与全部具体工程的施工",false,{"key":16,"text":17,"correct":14},"B","业主进行施工总承包管理单位招标时，应先确定工程总造价",{"key":19,"text":20,"correct":14},"C","施工总承包管理单位负责所有分包合同的招标投标工作",{"key":22,"text":23,"correct":24},"D","业主不需要等待施工图设计完成后再进行施工总承包管理单位的招标",true,"本题考查的是施工总承包管理。一般情况下，施工总承包管理单位不参与具体工程的施工；在进行对施工总承包管理单位的招标时，只确定施工总承包管理费，而不确定工程总造价；一般情况下，所有分包合同的招标投标、合同谈判以及签约工作均由业主负责；业主不需要等待施工图设计完成后再进行施工总承包管理的招标。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]