[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140584":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1140584,799,1,"单选题","某建设工程项目采用施工总承包管理模式，若施工总承包管理单位想承担部分工程的施工任务，则应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","通过投标竞争取得施工任务",true,{"key":16,"text":17,"correct":18},"B","通过项目业主委托取得施工任务",false,{"key":20,"text":21,"correct":18},"C","自行决定便可取得施工任务",{"key":23,"text":24,"correct":18},"D","通过施工总承包单位委托取得施工任务","本题考核的是施工总承包。 施工总承包管理模式的内涵是：业主方委托一个施工单位或由多个施工单位组成的施工联合体或施工合作体作为施工总包管理单位，业主方另委托其他施工单位作为分包单位进行施工。一般情况下，施工总承包管理单位不参与具体工程的施工，但如施工总承包管理单位也想承担部分工程的施工，可以参加该部分工程的投标，通过竞争取得施工任务。 综上所述，正确选项为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]