[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140572":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1140572,799,1,"单选题","（2019年真题）某土石方工程采用混合计价。其中土方工程采用总价包干14万元，石方工程采用综合单价合同，单价为100元\u002Fm3。该工程有关工程量和价格资料见下表，则该工程结算价款为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","34",false,{"key":16,"text":17,"correct":18},"B","39",true,{"key":20,"text":21,"correct":14},"C","37",{"key":23,"text":24,"correct":14},"D","42","P34-36 土方总包价格：14万元；石方工程结算价款为：2500m3*100元\u002Fm3=25万元； 工程结算价款为：14+25=39万余。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]