[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140571":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1140571,799,1,"单选题","建设项目工程总承包的基本出发点是借鉴工业生产组织的经验，实现建设生产过程的（ ）。2014",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","管理现代化",false,{"key":16,"text":17,"correct":14},"B","施工机械化",{"key":19,"text":20,"correct":14},"C","生产高效化",{"key":22,"text":23,"correct":24},"D","组织集成化",true,"建设项目工程总承包的基本出发点是借鉴工业生产组织的经验，实现建设生产过程的组织集成化，以克服由于设计与施工的分离致使投资增加，以及克服由于设计和施工的不协调而影响建设进度等弊病。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]