[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140559":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1140559,799,1,"单选题","某建设工程项目业主委托工程咨询单位为其提供全过程项目管理服务，并委托工程监理单位实施监理，若采用建设工程项目总承包模式，则设计阶段项目质量目标的决策者应是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程咨询单位",false,{"key":16,"text":17,"correct":14},"B","工程监理单位",{"key":19,"text":20,"correct":21},"C","项目总承包单位",true,{"key":23,"text":24,"correct":14},"D","业主","本题主要考查建设项目工程总承包的内涵。 根据《建设项目工程总承包管理规范》，工程总承包企业受业主委托，按合同约定对工程项目的勘察、设计、采购、施工、试运行等实行全过程或若干阶段的承包，对质量、工期、造价等向业主负责。因此，设计阶段项目质量目标的决策者应是项目总承包单位。 综上所述，本题正确选项为C项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]