[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140558":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1140558,799,1,"单选题","建设工程项目总承包的基本出发点是借鉴工业生产组织的经验，实现建设生产过程的（ ），以克服由于设计和施工不协调而影响建设进度。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织扁平化",false,{"key":16,"text":17,"correct":18},"B","组织集成化",true,{"key":20,"text":21,"correct":14},"C","组织柔性化",{"key":23,"text":24,"correct":14},"D","组织标准化","本题主要考查的是建设项目总承包的内涵。 建设项目工程总承包的基本出发点是借鉴工业生产组织的经验，实现建设生产工程的组织集成化，以克服由于设计与施工分离导致的投资增加，以及克服由于设计和施工的不协调而影响建设进度等弊端。 综上所述，正确选项为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]