[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140537":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1140537,799,1,"单选题","下列项目策划的工作内容中，属于项目实施管理策划的是（）。2018真题",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目实施期管理总体方案",false,{"key":16,"text":17,"correct":14},"B","生产运营期设施管理总体方案",{"key":19,"text":20,"correct":14},"C","生产运营期经营管理总体方案",{"key":22,"text":23,"correct":24},"D","项目风险管理与工程保险方案",true,"本题考查的是项目实施阶段策划的工作内容。选项A、B、C，属于项目决策阶段管理策划的内容。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]