[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140535":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1140535,799,1,"单选题","下列项目策划的工作内容中，属于项目决策阶段合同策划的是（）。2018真题",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目管理委托的合同结构方案",false,{"key":16,"text":17,"correct":14},"B","方案设计竞赛的组织",{"key":19,"text":20,"correct":21},"C","实施期合同结构总体方案",true,{"key":23,"text":24,"correct":14},"D","项目物资采购的合同结构方案","本题考查的是项目决策阶段策划的工作内容。选项A、B、D，属于项目实施阶段合同策划的内容。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]