[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140524":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1140524,799,2,"多选题","建设工程项目实施阶段组织策划的主要工作内容是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目管理工作流程",true,{"key":16,"text":17,"correct":18},"B","实施期组织总体方案",false,{"key":20,"text":21,"correct":14},"C","建立编码体系",{"key":23,"text":24,"correct":14},"D","任务分工和管理职能分",{"key":26,"text":27,"correct":14},"E","业主方项目管理的组织结构","ACDE","*本题主要考查实施阶段组织策划。 项目实施的组织策划，其主要工作内容包括： （1）业主方项目管理的组织结构； （2）任务分工和管理职能分工； （3）项目管理工作流程； （4）建立编码体系。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]