[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140522":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1140522,799,1,"单选题","建设工程项目实施阶段策划的主要任务是确定（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目建设的总目标",false,{"key":16,"text":17,"correct":14},"B","如何实现项目的目标",{"key":19,"text":20,"correct":14},"C","项目建设的指导思想",{"key":22,"text":23,"correct":24},"D","如何组织项目的建设",true,"本题主要考查建设工程项目实施阶段策划的主要任务。 建设工程项目实施阶段策划的主要任务是确定如何组织该项目的开发或建设。 综上所述，本题正确答案是D项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]