[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140519":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1140519,799,1,"单选题","建设工程项目实施阶段策划的主要任务是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","定义项目开发或减少的任务",false,{"key":16,"text":17,"correct":18},"B","确定如何组织该项目的开发或建设",true,{"key":20,"text":21,"correct":14},"C","确定建设项目的进度目标",{"key":23,"text":24,"correct":14},"D","编制项目投资总体规划","本题考核的是建设工程项目实施阶段策划的主要任务。 建设工程项目实施策划阶段的主要任务是确定如何组织该项目的开发或建设。其基本内容一般包括：项目实施的环境和条件的调查与分析；项目目标的分析和再论证；项目实施的组织策划、管理策划、合同策划、经济策划、技术策划和风险策划。 综上所述，正确选项为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]