[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140510":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1140510,799,1,"单选题","建设工程项目决策阶段策划中，属于组织策划的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","融资方案",false,{"key":16,"text":17,"correct":18},"B","项目编码体系分析",true,{"key":20,"text":21,"correct":14},"C","项目的规模、组成",{"key":23,"text":24,"correct":14},"D","项目效益分析","本题主要考查建设工程项目决策阶段策划的工作内容。 建设工程项目决策阶段策划的工作内容如下表： 由上表可知，属于组织策划的是项目编码体系分析。A项属于经济策划，D项属于经济策划，故错误。 综上所述，本题正确答案为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]