[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140499":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1140499,799,1,"单选题","承包商就已完工，经检验合格的工程提出支付申请，监理工程师复核后，业主批准支付申请，此工作程序属于（ ）流程。( 2015真题 )",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","物资采购工作",false,{"key":16,"text":17,"correct":14},"B","信息处理工作",{"key":19,"text":20,"correct":14},"C","设计工作",{"key":22,"text":23,"correct":24},"D","管理工作",true,"本题考查的是工作流程组织在项目管理中的应用。管理工作流程组织，如投资控制、进度控制、合同管理、付款和设计变更等流程。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]