[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140495":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1140495,799,1,"单选题","建设工程项目的工作流程图随工程进展应该（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","逐层细化",true,{"key":16,"text":17,"correct":18},"B","由项目工程师确定",false,{"key":20,"text":21,"correct":18},"C","一成不变",{"key":23,"text":24,"correct":18},"D","发生设计变更即需要修改","本题主要考查工作流程图。 工作流程组织的任务，即定义工作的流程。工作流程图应视需要逐层细化，如投资控制工作流程可细化为初步设计阶段投资控制工作流程图、施工图阶段投资控制工作流程图和施工阶段投资控制工作流程图等。 综上所述，本题正确选项为A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]