[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140478":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1140478,799,2,"多选题","施工单位的项目管理任务分工表可用于确定（ ）的任务分工。2014",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目各参与方",false,{"key":16,"text":17,"correct":18},"B","项目经理",true,{"key":20,"text":21,"correct":14},"C","企业内部各部门",{"key":23,"text":24,"correct":14},"D","企业内部各工作人员",{"key":26,"text":27,"correct":18},"E","项目各职能主管工作部门","BE","本题考查的是工作任务分工在项目管理中的应用。在项目管理任务分解的基础上，明确项目经理和费用（投资或成本）控制、进度控制、质量控制、合同管理、信息管理和组织与协调等主管工作部门或主管人员的工作任务，从而编制工作任务分工表。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]