[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140472":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1140472,799,1,"单选题","编制项目管理工作任务分工表的目的是为了明确（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目的构成及项目之间的关系",false,{"key":16,"text":17,"correct":14},"B","各项工作任务的重要程度",{"key":19,"text":20,"correct":21},"C","各项任务的负责部门及配合或参与部门（或个人）",true,{"key":23,"text":24,"correct":14},"D","各项工作之间的先后关系","本题考核的是工作任务分配的内容。 在工作任务分工表中应明确各项工作任务由哪个工作部门（或个人）负责，由哪些工作部门（或个人）配合或参与。在项目的进展过程中，应视必要对工作任务分工表进行调整。 综上所述，正确选项为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]