[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140457":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1140457,799,1,"单选题","某建设工程项目的规模不大，参与单位不多，为提高管理效率，避免出现矛盾指令。宜采用（ ）模式。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","线性组织结构",true,{"key":16,"text":17,"correct":18},"B","混合组织机构",false,{"key":20,"text":21,"correct":18},"C","矩阵组织机构",{"key":23,"text":24,"correct":18},"D","职能组织机构","本题考核的是建设工程项目的组织结构。 在线性组织结构中，每一个工作部门只能对其直接的下属部门下达工作指令，每一个工作部门也只有一个直接的上级部门，即每一个工作部门只有一个指令源，避免了由于矛盾的指令而影响组织系统的运行。 综上所述，正确选项为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]