[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140442":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1140442,799,1,"单选题","关于项目结构分析的说法，正确的是（）。2018真题",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","同一个建设工程项目只有一个项目结构的分解方法",false,{"key":16,"text":17,"correct":18},"B","居住建筑开发项目可根据建设的时间对项目结构进行逐层分解",true,{"key":20,"text":21,"correct":14},"C","群体项目最多可进行到第二层次的分解",{"key":23,"text":24,"correct":14},"D","单体工程不应再进行项目结构分解","本题考查的是项目结构图。选项A，项目结构分解并没有统一的模式，因此可以有多种分解方法。选项C，群体项目可以逐层分解，不是最多可进行到第二层次；选项D，单体工程如有必要，也应进行项目结构分解。参见教材5。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]